From Demo to Drywall: What Every Montreal Renovation Timeline Should Include

Montreal Renovation Timeline

From Demo to Drywall: What Every Montreal Renovation Timeline Should Include

A typical Montreal renovation timeline runs about 3–5 weeks for a bathroom, 6–9 for a kitchen, and 3–6 months for a whole home — across seven phases from planning and permits to final fixtures. Permits alone take 2–6 weeks, and the city’s transformation permit costs $9.80 per $1,000 of work. Here’s the phase-by-phase breakdown.

Whether you’re upgrading a Plateau duplex or transforming a suburban split-level in Kirkland, every successful project starts with a realistic Montreal renovation timeline. Yet too many homeowners overlook the essential steps between demolition and drywall — and that’s where delays, budget overruns, and headaches begin.

This article breaks down a smart, phase-by-phase renovation timeline specific to Montreal properties — including local permit delays, weather realities, and trade scheduling bottlenecks. Whether you’re hiring a general contractor or coordinating trades yourself, here’s what to expect.

Phase 1: Planning & Permits (2–6 Weeks)

Before you even think about dust masks and hammers, you need plans — and permits. In Montreal, most major renovations require one or both of the following:

Expect longer approval times in historic neighborhoods (like Villeray or Le Plateau-Mont-Royal) or if your project alters structure or façade. The transformation permit itself costs $9.80 for every $1,000 of work, with a $167.40 minimum for a residential building, per the City of Montréal.

Tasks in this phase:

  • Hire an architect or designer
  • Get plans drawn
  • Submit permit applications
  • Order lead-time items (windows, flooring, etc.)

Pro tip: Working with a contractor like DemoPrep can speed up permitting by managing drawings and submissions for you.

Phase 2: Demolition (1–2 Weeks)

This is where the transformation begins. A proper demolition includes more than smashing walls — it’s about surgical removal of materials while protecting what stays.

DemoPrep’s Montreal demolition services include:

  • Interior gut-outs
  • Bathroom and kitchen removal
  • Drywall and flooring demo
  • Garage or shed removal

We also provide dust barriers, waste bins, and licensed hauling to keep your project safe and legal. Read our guide: Montreal demolition waste rules.

Phase 3: Structural Work (1–3 Weeks)

After demolition, the framing and structure phase begins. This may include:

  • New walls or partitions
  • Beam and post installs for open-concept layouts
  • Window or door relocations

During this time, trades such as plumbers, electricians, and HVAC pros do their “rough-in” installations — meaning they run wires and pipes before walls are closed up.

Common delays: waiting on inspections from Montreal city officials before closing walls.

Phase 4: Insulation & Inspections (3–5 Days)

Once all rough-ins are complete and approved, insulation is installed. In most cases, a building inspector must approve this before drywall goes up.

Tips:

  • Use spray foam in hard-to-seal areas (like rim joists)
  • Make sure air/vapor barriers comply with Quebec code

Phase 5: Drywall & Finishing (1–2 Weeks)

Now it’s time to close up the walls and start finishing. This includes:

  • Hanging and taping drywall
  • Mudding, sanding, and priming
  • Painting base coats

Humidity can slow drying times, so expect delays if you’re renovating in spring or fall without adequate heat.

Phase 6: Flooring, Trim & Cabinetry (2–4 Weeks)

This phase overlaps with final painting and may include:

  • Hardwood or tile installation
  • Baseboards and crown molding
  • Kitchen cabinet install
  • Countertop templating and fabrication

Cabinet shops in Montreal can have lead times of 4–8 weeks, so order early. Appliance and plumbing fixture delivery may also affect timing.

Phase 7: Final Fixtures & Touchups (1 Week)

Final tasks before move-in:

  • Install lighting, outlets, and switches
  • Connect plumbing fixtures
  • Final paint touchups
  • Cleanup and client walkthrough

If your reno is being done for resale, this is where staging and photography happen.

Total Timeline: What to Expect

Renovation Type Typical Timeline
Small Bathroom 3–5 weeks
Kitchen Renovation 6–9 weeks
Full Floor Renovation 10–14 weeks
Whole Home Renovation 3–6 months

Tip: Renovating in winter can actually reduce wait times, as contractor demand drops between January and March in Montreal.

Why Trust DemoPrep With Your Timeline?

We’ve completed everything from single-room demolitions to full home rebuilds across Montreal’s boroughs. Our team coordinates all trades, permits, inspections, and material logistics so your Montreal renovation timeline stays on track — and on budget.

Contact us today to start planning your ideal timeline and get a transparent quote for demolition, renovation, or both.